Hurricane Pride is a group of parents, student athletes, coaches, alumni, and community members that have come together to support the educational and athletic programs for Hoosac Valley Middle and High School. Our belief is that our future is with our children and we are focusing our efforts on the development of a strong body and mind for our youth. A well rounded child is a happy and successful future leader of our community.
Hurricane Pride has identified two projects they will be raising money: 1) equipment for our strength and conditioning room at the newly renovated middle and high school and 2) the building of a multi-use concession building. Both of these projects are not within the scope of the renovation project and have become the focus of this group. Our goal is $70,000 of which $29,500 will be earmarked for weight/training equipment and approximately $40,500 towards the building of the concession building.
The strength and conditioning room will be equipped with multi-use squat and bench racks with rubber platforms, rubber weights, glute ham developers, medicine balls, ropes, dumbbells, and soft impact Plyo boxes. This equipment will be available to all students so that they can condition within their own school. The concession will be available for use by baseball, cross-country, football, soccer, softball, and track and will have storage space and bathroom facilities. Donated building services are being sought for the construction of the building, but monies will be needed for supplies, plumbing, and electric. Donations to this effort may be considered tax deductible.
Our efforts will kickoff on July 9, 2012.Donations to these projects may be made through an online Pay Pal account or by mailing a check or money order to the high school c/o Hurricane Pride. Additional information is located at: www.acrsd.net, Facebook.com/HVPride, and www.hurricanepride.com.
Hurricane Pride will also be providing the opportunity to purchase inscriptions on the brick pavers that are part of the renovated arts entrance at HVMHS. The monies will also be earmarked for the strength and conditioning room equipment and multi-sport concession building. Order forms will be located at Hurricane Pride on Facebook and the District’s website.
A sample of the brick pavers will be available at HiJinx on July 30 at the Hurricane Booth. In addition to the availability of purchasing inscriptions on the brick pavers, the group will be planning a fundraising dinner event with more information to follow.
Monetary updates to our fundraising efforts will be posted on Hurricane Pride, Facebook and the school’s website so you can watch us grow.
Alumni, family and friends, please help support our efforts!
Regina Hill – Hurricane Pride Coordinator
May Photos
Posted by Hurricane Pride in Construction Updates on June 14, 2012
Catching up on construction photos, check out this album fromMay:
![]() |
| May 2012 |
April Photos
Posted by Hurricane Pride in Construction Updates on June 13, 2012
March Photos
Posted by Hurricane Pride in Uncategorized on June 12, 2012
Here’s an album for March:
![]() |
| March 2012 |
Photo Updates, Project is Rolling!
Posted by Hurricane Pride in Construction Updates on June 11, 2012
Sorry for the delay in updates. All photos have been updated on facebook but now they are available here as well. One month of photos will be posted each day this week!!
Catching up on the month of February below:
![]() |
| February 2012 |
Lab Ceiling, Middle School Gym, More Atrium Views
Posted by Hurricane Pride in Construction Updates on February 10, 2012
For the week of February 2, 2012:
High School Lab Ceiling Installation Begins
Atrium looking towards middle school entrance
Bathroom tile installation
Middle school Gym
Main electrical room
Updates all over the building! Cafeteria, Atrium, Gym, Lab, Main Entrance
Posted by Hurricane Pride in Construction Updates on February 3, 2012
Photos taken January 16-18, 2012:

Cafeteria plumbing

New paint in gym

Middle school entrance from atrium area

Pre-cast panel installed near main entrance

Atrium glass installation nearly complete

Ceiling grid in a lab room

Bathroom tile installation has begun

Wall erected in west addition

High school entrance from atrium area

Atrium glass installation has begun

Wall studs erected in administrative area

Red brick installed at Theatre entrance
Painting Continues, Main Entrance, Gyms, Locker Room, Atrium
Posted by Hurricane Pride in Construction Updates on February 3, 2012
For the week ending January 13, 2012:

Painting in a classroom and heating unit awaiting installation

West side of main entrance

East side of main entrance

Transformer in place

Steel over pool for middle school gym floor. Rainwater harvest tanks below

View of courtyard from cafeteria windows

Gym walls getting painted

Locker room footings to be poured

Painting of beams in high school gym ceiling almost complete

Bathroom ready for tile prep

Atrium framing is ready for glass

Administrative Office space

Ceiling grid in classroom gets installed
Atrium Takes Shape, Middle School Gym Floor, Locker Rooms, Library, Painting in High School Gym!
Posted by Hurricane Pride in Construction Updates on February 1, 2012
For the week of January 6, 2012:
Installation for frame of atrium has begun
Foam insulation at doorway to courtyard
Prep for concrete pad for gear in main electrical room
Plumbing for locker rooms
Steel erection for middle school gym floor
Painting has begun in high school gym!
Restroom prep near gym entrance
Progress in library
Painting, Rainwater collection, Music Room, Steel Reinforcements
Posted by Hurricane Pride in Building Committee on January 30, 2012
For the week of December 30, 2011:

Steel reinforcement for a small hole cut into a hallway

Installation of water pipes for pump room

Spray fire retardant applied on ceiling of new addition

Steel reinforcement for a small hole cut into a pre-stressed “T”

A full lot of workers on the site each day

Music room wall studs

Roof mounted heating unit is being lowered into place

Pool is now ready for rainwater collection tanks

New roof fascia panels

Painting has begun