Updates all over the building! Cafeteria, Atrium, Gym, Lab, Main Entrance
Posted by Hurricane Pride in Construction Updates on February 3, 2012
Photos taken January 16-18, 2012:

Cafeteria plumbing

New paint in gym

Middle school entrance from atrium area

Pre-cast panel installed near main entrance

Atrium glass installation nearly complete

Ceiling grid in a lab room

Bathroom tile installation has begun

Wall erected in west addition

High school entrance from atrium area

Atrium glass installation has begun

Wall studs erected in administrative area

Red brick installed at Theatre entrance
Mid-December and Work Continues
Posted by Hurricane Pride in Construction Updates on January 7, 2012
From December 13 & 15:
Masonry work coming together in new south (main) entrance
Footing preparations in cafeteria
Wiring installation
New fencing at track
Library ductwork insulation
Steel supports needed for one new roof penetration
Cafeteria footing poured
New roof over Main Entrance
New boilers!
New classroom wiring
High school gym old vs. new Kelwall panels