Posted by Hurricane Pride in Construction Updates on February 3, 2012
For the week ending January 13, 2012:

Painting in a classroom and heating unit awaiting installation

West side of main entrance

East side of main entrance

Transformer in place

Steel over pool for middle school gym floor. Rainwater harvest tanks below

View of courtyard from cafeteria windows

Gym walls getting painted

Locker room footings to be poured

Painting of beams in high school gym ceiling almost complete

Bathroom ready for tile prep

Atrium framing is ready for glass

Administrative Office space

Ceiling grid in classroom gets installed
Atrium Takes Shape, Middle School Gym Floor, Locker Rooms, Library, Painting in High School Gym!
Posted by Hurricane Pride in Construction Updates on February 1, 2012
For the week of January 6, 2012:
Installation for frame of atrium has begun
Foam insulation at doorway to courtyard
Prep for concrete pad for gear in main electrical room
Plumbing for locker rooms
Steel erection for middle school gym floor
Painting has begun in high school gym!
Restroom prep near gym entrance
Progress in library