Middle School Gym, Wiring, Insulation
Posted by Hurricane Pride in Construction Updates on November 30, 2011
Photos from the week of November 29, 2011:
Floor prep in music room
New Kelwall panel installation commenced in south side of middle school gym
New window sill installation on north side of middle school gym (old pool)
Courtyard drainage system being installed
Spray foam applied to a wall in the high school lab
Wiring in process
Electrical, New Windows, Arts Entrance & More Work on Additions
Posted by Hurricane Pride in Construction Updates on November 29, 2011
New photos from the school project from the week of November 22nd:
Courtyard Addition Masonry and Steelwork
Data and Communications wiring and sprinkler system being installed
Electrical conduit entry
The Arts Entrance
New window installation has begun
Pool windows removed
Birdseye of the pool
Interior lab windows and wall studs in place
New main entrance area takes shape
Interior lab wall insulated with spray foam
Roof work being prepared at south entrance
How do you think the project is coming along? Let us know!
Last Week of October – Roof Panels, Windows, and Seismic Footing!
Posted by Hurricane Pride in Construction Updates on November 22, 2011
Photos from the week of October 27, 2011:
Roof panels installed over the new main entrance
Cleaned out auditorium
New drainage for the football field
Removal of fascia panels in courtyard in preparation for the new addition
Window openings are prepped for new window installation
New seismic footing installed in the music room